Ofgem consults on loosening cap and floor regime for interconnectors

Ofgem is consulting on a series of variations to the cap floor and regime requested by the developers of the Greenlink and NeuConnect interconnectors to Ireland and Germany.

Without the changes, the companies claim the projects will struggle to secure sufficient financing and could be delayed or cancelled.

Both have already been given the all-clear by Ofgem to operate under the cap and floor regime on generic terms. The scheme entitles interconnector operators to receive top-up payments from consumers when their revenues fall below the floor but also requires them to return money to customers when their revenues exceed the cap.

The regulator has previously estimated the projects to be worth £2.36 billion in terms of net benefits to consumers but wants to ensure that the proposed changes do not transfer too much value to developers. It is therefore seeking views from stakeholders on five key variations, which are:

The consultation document notes that the four other electricity interconnectors to be approved under the regime are all being funded by developer National Grid Ventures from its own balance sheet.

“The likelihood of balance sheet developers similar to National Grid Ventures stepping forward to fund these two projects under the default regime is unclear,” the documents adds.

“In any event, we expect that the balance sheet financing route would likely result in project delays. We also consider that ensuring the regime is fit for a broad range of financing solutions, including project finance, would benefit consumers in the long run.”

Ofgem said its initial impact assessment suggests the fourth and fifth variations should be rejected and the rest accepted. It is aiming to make a decision in early 2020.

The deadline for responses is 28 November.